[Nov 15, 2021] Pass C-ACTIVATE13 Review Guide, Reliable C-ACTIVATE13 Test Engine
C-ACTIVATE13 Test Engine Practice Test Questions, Exam Dumps
NEW QUESTION 83
What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
Response:
- A. Plan -> Build -> Run -> Sustain
- B. Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
- C. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
- D. Plan -> Design -> Build -> Operate
Answer: C
NEW QUESTION 84
What are some of the key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:
- A. Based on Ready-to-use Content
- B. Delta-based
- C. Cloud Ready
- D. Fixed scope
- E. On premise only
Answer: A,B,C
NEW QUESTION 85
In which phase do you create an ordered list of everything that is known to be needed in the product"?
Please choose the correct answer.
Response:
- A. Prepare
- B. Deploy
- C. Explore
- D. Realize
Answer: D
NEW QUESTION 86
What is a Strategy Level 0 (LO) artifact?
Please choose the correct answer.
Response:
- A. Optional information that is NOT important for project activities
- B. Preliminary strategy developed by the customer to approach the project in a specific work stream
- C. Approach document that is developed by a united Project Team (partner + customer)
- D. Project result that is developed solely by the partner
Answer: B
NEW QUESTION 87
How are the build and test tasks planned and executed in the Realize phase?
Please choose the correct answer.
Response:
- A. By executing regression tests after each iteration
- B. By using incremental build in fixed-scope iteration
- C. With Q-Gates for sign off after each iteration
- D. By using the sprint backlog list as input for each iteration.
Answer: B
NEW QUESTION 88
In which SAP Activate methodology phase does the team complete the Transformation Strategy?
Please choose the correct answer.
Response:
- A. Prepare
- B. Deploy
- C. Realize
- D. Explore
Answer: A
NEW QUESTION 89
What tool do you use to configure an SAP Business Suite on-premise solution?
Please choose the correct answer.
Response:
- A. Expert Configuration
- B. Configuration Composer
- C. ABAP Workbench
- D. SAP Implementation Guide
Answer: D
NEW QUESTION 90
What are the three elements of SAP Activate?
There are 3 correct answers to this question.
Response:
- A. Content
- B. SAP Solution Manager
- C. Focused Build
- D. Methodology
- E. Tools
Answer: A,D,E
NEW QUESTION 91
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content?
Please choose the correct answer.
Response:
- A. Navigate by work stream
- B. Navigate by Project Team Member Role
- C. Navigate by RACI matrix accountability
- D. Navigate by assigned Delivery Mode
Answer: A
NEW QUESTION 92
In which phase do you execute the User Acceptance Test?
Please choose the correct answer.
Response:
- A. Build and Test
- B. Final Preparation
- C. Deploy
- D. Realize
Answer: D
NEW QUESTION 93
Which of the following tools is used to install SAP S/4HANA.
Please choose the correct answer.
Response:
- A. SWPM (Software Provisioning Manager)
- B. Data Migration server
- C. SAP Solution Manager
- D. Cloud Application Library
Answer: A
NEW QUESTION 94
In which phase should you first run the SAP Readiness Check for SAP S/4HANA in a "Selective Data Transition" transition path, in a System Consolidation scenario that includes conversion from SAP ERP?
Please choose the correct answer.
Response:
- A. Prepare
- B. Realize
- C. Explore
- D. Discover
Answer: D
NEW QUESTION 95
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud' transition path?
Please choose the correct answer.
Response:
- A. Setup and Enablement
- B. Fit-to-standard
- C. Simplification and Custom Code Impact Analysis
- D. Solution Validation and Delta Design
Answer: B
NEW QUESTION 96
Which of the following are available in the initial SAP Methodologies JAM Page?
There are 2 correct answers to this question.
Response:
- A. Roadmaps
- B. Summary
- C. Task description
- D. Accelerators
Answer: A,D
NEW QUESTION 97
In which phase will the customer develop a preliminary strategy for building a target Operations and Support organizational model?
Please choose the correct answer.
Response:
- A. Explore phase
- B. Run phase
- C. Discover phase
- D. Prepare phase
Answer: D
NEW QUESTION 98
What is the purpose of the SAP Activate Methodology?
Please choose the correct answer.
Response:
- A. To accelerate the initial implementation of SAP S/4HANA
- B. To manage project and solution documentation
- C. To enable access to the SAP ecosystem
- D. To provide end-to-end integrated application lifecycle management
Answer: A
NEW QUESTION 99
Which of the following is not correct about Fit/Gap Analysis?
There are 2 correct answers to this question.
Response:
- A. Prioritize delta requirement and gaps.
- B. Validate pre-activate and pre-assembled solution in the development system.
- C. Minimize the needs for rework during realization.
- D. Drive towards adopting customers processes.
Answer: B,D
NEW QUESTION 100
Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase?
There are 2 correct answers to this question.
Response:
- A. Quality Gate Checklist
- B. RICEF Specification Template
- C. Solution Validation Workshop
- D. Sprint Backlog Template
Answer: B,C
NEW QUESTION 101
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
Please choose the correct answer.
Response:
- A. Prepare
- B. Realize
- C. Explore
- D. Deploy
Answer: D
NEW QUESTION 102
......
SAP Activate Project Manager Certification Exam Details:
| Passing Score | C_ACTIVATE13 - 65% |
| Schedule Exam | SAP Training |
| Reference Books | ACT100 (SAP S/4HANA 1809) ACT200 (SEE COURSE DETAIL) |
| Exam Price | $550 (USD) |
| Level | Associate |
| Sample Questions | SAP Activate Project Manager Certification Sample Questions |
| Exam Name | SAP Certified Associate - SAP Activate Project Manager |
| Exam Code | C_ACTIVATE13 |
| Number of Questions | 80 |
| Duration | 180 mins |
SAP C-ACTIVATE13 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Transition Path "New Implementation SAP S/4HANA Cloud" 8% - 12% | Describe concepts, landscape overview, and specifics in Workstreams related to implementing SAP S/4HANA Cloud. |
| Transition Path "Selective Data Transition" < 8% | Describe concepts, landscape overview and specifics in Workstreams related to “Selective Data Transition” Transition Path. |
| Transition Path "New Implementation SAP S/4HANA On Premise" < 8% | Describe concepts, landscape overview and specifics in Workstreams related to implementing SAP S/4HANA On Premise. |
| Workstreams Overview > 12% | Describe concepts, artefact flows, accelerators, tools and roles for each Workstream within SAP Activate Methodology |
| Agile Project Planning 8% - 12% | Describe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog |
| SAP Activate Overview > 12% | Define factors influencing SAP Activate, its purpose and place among other frameworks |
| Agile Project Delivery > 12% | Describe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects |
| SAP Activate Elements > 12% | Provide an overview of content, tools and methodology elements of SAP Activate Solution Implementation Framework. Include Fit to Standard |
| Transition Path "System Conversion" < 8% | Describe concepts, landscape overview and specifics in Workstreams related to “System Conversion” Transition Path. |
100% Free C-ACTIVATE13 Daily Practice Exam With 169 Questions: https://www.testkingpass.com/C-ACTIVATE13-testking-dumps.html
C-ACTIVATE13 exam torrent SAP study guide: https://drive.google.com/open?id=1g0F_rnt_7-moT5IG5c_Ht9RJ7rv9-Yzf