What is the duration of the PR2F Exam

  • Length of Examination: 1 hour
  • Passing Score: 55%
  • Format: Multiple choices, multiple answers
  • Number of Questions: 60

For more info read reference

PRINCE2-Foundation Exam Source

 

NEW QUESTION 194
Which process is used to define how baselines will be established and controlled?

  • A. Controlling a stage
  • B. Directing a project
  • C. Starting up a project
  • D. Initiating a project

Answer: C

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality

 

NEW QUESTION 195
Which statement about the Directing a Project process is true?

  • A. Covers the day-to-day activities of the Project Manager
  • B. Provides a mechanism for the Project Board to assure that there is continuedbusiness justification
  • C. Ensures there are regular progress meetings
  • D. Begins on completion of the Initiating a Project process

Answer: B

 

NEW QUESTION 196
Which is a purpose of the Managing Product Delivery process?

  • A. Establish solid foundations for the project
  • B. Enable the Project Board to request updates to the current Team Plan
  • C. Provide a controlled link between the Project Manager and the Team Manager(s)
  • D. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package

Answer: C

 

NEW QUESTION 197
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

  • A. Techniques
  • B. Principles
  • C. Processes
  • D. Themes

Answer: B

 

NEW QUESTION 198
Which is a purpose of a Lessons Log?

  • A. Raise improvements with Project Assurance
  • B. Note any lessons that are raised in Checkpoint Reports
  • C. Record that corrective action is being taken
  • D. Escalate lessons to the Project Board

Answer: B

 

NEW QUESTION 199
What is an advantage of dividing the project into stages?

  • A. Detailed plans can be prepared closer to the time events will take place
  • B. the project board can delegate management of the project to team managers
  • C. The project brief can be updated towards the end of each stage
  • D. The project can be authorized by the project manager on a stage by stage basis

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:

 

NEW QUESTION 200
What should be considered when defining the number of management stages in a project?

  • A. When key decisions need to be made
  • B. When highlight reports will be submitted
  • C. When the team managers are available
  • D. When project support will be available

Answer: A

Explanation:
Explanation
Reference https://www.prince2primer.com/prince2-management-and-technical-stages/

 

NEW QUESTION 201
What is a supplier of a PRINCE2 project responsible for?

  • A. Providing resources to deliver the project outputs
  • B. Establishing the project's governance
  • C. Realizing the benefits from the project
  • D. Providing the project mandate

Answer: A

Explanation:
Explanation/Reference:
Reference http://prince2.wikidot.com/senior-supplier

 

NEW QUESTION 202
What information should be recorded in the quality register?

  • A. Planned activities to determine whether the products are fit for purpose
  • B. Potential threats to the project's objectives and how they will be managed
  • C. Lessons that the project will capture and use during the project
  • D. Off-specifications that will occur during the project

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: https://mplaza.pm/prince2-quality-register-template/

 

NEW QUESTION 203
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

  • A. Those with a financial interest in the project
  • B. Those who will manage the project on a day-to-day basis
  • C. Those who will specify the desired outputs of the project
  • D. Those who will create the project's outputs

Answer: B

Explanation:
Section: Volume A
Explanation/Reference:

 

NEW QUESTION 204
Which process covers the work done by external suppliers who may NOT be using PRINCE2?

  • A. Closing a Project
  • B. Directing a Project
  • C. Managing a Stage Boundary
  • D. Managing Product Delivery

Answer: D

 

NEW QUESTION 205
What should be considered when defining the number of management stages in a project?

  • A. When key decisions need to be made
  • B. When highlight reports will be submitted
  • C. When the team managers are available
  • D. When project support will be available

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-management-and-technical-stages/

 

NEW QUESTION 206
Identify the missing words in the following sentence.
The 'directing a project' process starts when [ ? ] and is triggered by the request to initiate a project.

  • A. the 'starting up a project' process is completed
  • B. the project mandate has been approved by the project board
  • C. the project board has agreed the project strategies
  • D. corporate, programme management or the customer have authorized a project

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.siliconbeachtraining.co.uk/blog/prince2-directing-project-process-dp

 

NEW QUESTION 207
Which of the following statements about the Closing a Project process are true?
1.The Closing a Project process provides a fixed point for the receipt of completed Work
2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.

  • A. Both 1 and 2 are true
  • B. Neither 1 or 2 are true
  • C. Only 1 is true
  • D. Only 2 is true

Answer: D

 

NEW QUESTION 208
Which of the following is the Business Case used for during the Managing a Stage
Boundary process?

  • A. Enable the Project Board to decide whether or not to authorize the project
  • B. Justify the initiation of a project
  • C. Justify the continuing viability of the project
  • D. Enable the Project Board to decide whether or not to authorize project closure

Answer: C

 

NEW QUESTION 209
Which is NOT a type of issue?

  • A. An off-specification
  • B. A problem/concern
  • C. A request for change
  • D. A constraint

Answer: D

 

NEW QUESTION 210
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required

  • A. 1 and 2
  • B. 1 and 4
  • C. 3 and 4
  • D. 2 and 3

Answer: D

Explanation:
Explanation
Reference https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2

 

NEW QUESTION 211
Which is a responsibility of a risk owner?

  • A. Own and authorize the use of the risk budget to fund risk responses
  • B. Identify risks to the project that might occur in their department
  • C. Determine project risk appetite
  • D. Manage, monitor and control all aspects of an assigned risk

Answer: D

 

NEW QUESTION 212
Which two roles are linked by the Managing Product Delivery process?

  • A. Team Manager and external supplier
  • B. Project Manager and Team Manager
  • C. Project Board and Project Manager
  • D. Corporate or programme management and Project Board

Answer: B

Explanation:
Section: Volume A

 

NEW QUESTION 213
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?

  • A. Directing a project
  • B. Managing a stage boundary
  • C. Managing product delivery
  • D. Initiating a project

Answer: C

Explanation:
Explanation
Reference https://www.prince2.com/blog/the-7-principles-themes-and-processes-of-prince2/

 

NEW QUESTION 214
Which is an objective of the 'directing a project' process?

  • A. To review and approve a project mandate
  • B. To obtain approval for completed products
  • C. To define how risks, issues and changes will be managed
  • D. To ensure corporate or programme management has an interface to the project

Answer: D

Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Directing_a_Project#Objective

 

NEW QUESTION 215
What is described as an organization's unique attitude towards risk taking

  • A. Risk appetite
  • B. Risk tolerance
  • C. Risk management
  • D. Risk evaluation

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 216
How does the project board use the 'manage by stages' principle to control the project?

  • A. By reviewing project viability at defined intervals
  • B. By ensuring that the benefits are managed and controlled
  • C. By approving the project management team
  • D. By reviewing previous project closure documentation

Answer: A

Explanation:
Reference http://prince2.wiki/Manage_by_stages

 

NEW QUESTION 217
Which is a purpose of a Lessons Log?

  • A. Raise improvements with Project Assurance
  • B. Note any lessons that are raised in Checkpoint Reports
  • C. Record that corrective action is being taken
  • D. Escalate lessons to the Project Board

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 218
Which is a purpose of the 'initiating a project' process?

  • A. To decide if it is worthwhile to initiate a project
  • B. To identify the number of work packages required
  • C. To decide on the project approach
  • D. To establish solid foundations for a project

Answer: D

Explanation:
Explanation
Reference http://prince2.wiki/Initiating_a_Project#Objective

 

NEW QUESTION 219
......