Get Instant Access to Project-Management Practice Exam Questions [Q23-Q42]

Share

Get Instant Access to Project-Management Practice Exam Questions

Reliable Study Materials & Testing Engine for Project-Management Exam Success!


NCARB Project-Management Exam Syllabus Topics:

TopicDetails
Topic 1
  • Contracts: This section of the exam measures the skills of project managers and covers the analysis of contracts that govern the relationships between architects, owners, contractors, and consultants. It highlights verifying adherence to agreements, interpreting key contractual elements, and ensuring consultant work is properly integrated into the project.
Topic 2
  • Project Execution: This section of the exam measures skills of architectural associates and covers the management of project execution through administrative procedures rather than design decisions. It addresses evaluating budgets, managing scope changes, preparing project documentation in line with delivery methods, and securing necessary approvals from relevant authorities.
Topic 3
  • Resource Management: This section of the exam measures the skills of project managers and covers how to determine the right team composition and manage time allocation for successful project delivery. It focuses on evaluating criteria for assembling teams and ensuring resources are properly managed to execute the project within agreed terms.
Topic 4
  • Project Quality Control: This section of the exam measures skills of project managers and covers procedures for ensuring quality and maintaining the Standard of Care throughout the project. It focuses on applying regulatory requirements, reviewing documentation for quality, reducing risks and liabilities, and managing the design process to preserve its objectives
Topic 5
  • Project Work Planning: This section of the exam measures the skills of architectural associates and covers the development and communication of an effective project work plan. It emphasizes maintaining schedules, setting clear criteria for work planning, and ensuring consistent communication with stakeholders, including owners, contractors, consultants, and internal staff.

 

NEW QUESTION # 23
During the initial construction documents phase meeting, the owner states a strong desire to decrease the time required for the construction documents phase. The owner plans to submit the documents to the building department early for the building permit. Although the project is currently on schedule, the architect plans to comply with the owner's request.
Which action should the architect take?

  • A. Discuss the current work plan with the owner and offer to expand staffing and reduce the schedule for additional services
  • B. Review with the owner a reorganized layout for the construction drawing set to use fewer sheets and fewer details
  • C. Recommend to defer any decision until the documents are 25% completed and more information is available
  • D. Agree with the owner's compressed schedule if the owner agrees to reduce significantly the time for the owner's review of the documents

Answer: A

Explanation:
Verified Answer
Comprehensive Detailed Explanation:
To responsibly reduce the time required for the Construction Documents (CD) phase, the architect should discuss the staffing strategy and the additional resources needed to compress the schedule. This constitutes an additional service, as compressing the schedule requires added effort and cost. Offering to expand staffing allows the firm to maintain quality while meeting the owner's request.
References:


NEW QUESTION # 24
What is a critical factor in managing project risk?

  • A. Ignoring minor delays to avoid panic
  • B. Assigning all risk to the contractor
  • C. Avoiding communication with the owner about risks
  • D. Identifying risks early and developing mitigation strategies

Answer: D

Explanation:
Effective risk management begins with early identification of potential risks and developing strategies to mitigate or respond to them. This includes scheduling, budget, design, and regulatory risks. Assigning all risk to contractors is unrealistic; avoiding communication worsens issues. ARE 5.0 PjM stresses proactive risk identification, communication, and management as key to project success.


NEW QUESTION # 25
During the bidding phase, what is the architect's role regarding addenda?

  • A. Issuing clarifications or changes to the bidding documents to all bidders
  • B. Selecting the winning bidder based on cost
  • C. Negotiating contract terms with the contractor
  • D. Approving subcontractor selections

Answer: A

Explanation:
Addenda are formal clarifications or modifications to the bidding documents issued during the bidding phase.
The architect prepares and issues addenda to all prospective bidders to clarify, correct, or change the documents. This ensures all bidders have the same information for fair and accurate proposals. Selecting bidders, negotiating contracts, and approving subcontractors are typically owner or contractor responsibilities.
ARE 5.0 PjM stresses the importance of managing bidding documents and communications during this phase.


NEW QUESTION # 26
After construction begins, an owner asks the architect to select a different roof material. The architect wants to manage the risk associated with this change.

  • A. Place a note in the project file to detail roof options and the final decision.
  • B. Contact roofing suppliers to request product specifications to select a replacement.
  • C. Contact the contractor to request a change order.
  • D. Write a memorandum to the owner to describe the owner's request for a change.

Answer: D

Explanation:
Verified Answer
The correct risk management approach is to document the owner's request clearly before taking any action. A written memorandum becomes part of the formal record and clarifies scope, timing, and potential cost implications. This protects the architect from misinterpretation or dispute.
Verbal or informal changes are a legal and professional risk.
Once documented, changes can proceed via appropriate channels (change order or construction change directive).
Reference: AIA B101 §4.2.2; A201 §7.3
NCARB ARE 5.0 Handbook - PjM Content Area 5: Project Execution


NEW QUESTION # 27
What is the architect's role regarding shop drawings?

  • A. Preparing and submitting them to the owner
  • B. Approving changes without owner input
  • C. Reviewing them for compliance with design intent
  • D. Issuing shop drawings to subcontractors

Answer: C

Explanation:
Shop drawings are prepared by contractors or suppliers to show fabrication and installation details. The architect reviews them to ensure compliance with design intent and contract documents but does not prepare or distribute them. Any changes found during review may require owner approval or change orders. ARE 5.0 PjM covers architect's review responsibilities in construction administration.


NEW QUESTION # 28
An architect is working on a design-build project for a large skyscraper. The architect has completed a conceptual design, finalized the contracts, and hired consultants. The schematic design phase is set to begin in one week.
Which items or tasks are important for the architect to complete during this time? Check the three that apply.

  • A. Create a project schedule
  • B. Prepare building permit application
  • C. Coordinate the curtain wall detailing with the envelope
  • D. Send consultants project constraints
  • E. Identify FF&E vendors
  • F. Ask consultants to review information and provide input

Answer: A,D,F

Explanation:
Verified Answer
At the outset of schematic design, the architect must coordinate with consultants and communicate constraints and expectations to keep the project aligned with goals. Building permits are typically addressed in the construction documents phase. FF&E coordination and curtain wall detailing occur later in design development and construction documents.
Coordination and planning at schematic design are crucial to project integration.
Reference: AIA B101 §3.2 - Schematic Design Phase
NCARB ARE 5.0 Handbook - PjM Content Area 1 and 4


NEW QUESTION # 29
The main goals on a large project are ease of communication and commitment from the project team.
Which scheduling technique should be used?

  • A. Milestone chart
  • B. Interactive bar chart
  • C. Critical path method

Answer: B

Explanation:
Interactive bar charts are ideal for large projects where team commitment and communication are priorities.
Unlike a simple milestone chart or the more complex Critical Path Method (CPM), interactive bar charts provide a visual, time-based representation of tasks that facilitates easy understanding across disciplines.
When developed in a collaborative setting (such as pull-planning or in-person planning sessions), these charts help the project team see their roles, identify dependencies, and commit to deliverables.
The ARE 5.0 Handbook (Project Management division) describes interactive bar charts as excellent tools for collaborative environments where schedule visibility and team accountability are essential.
These charts promote communication across team members and are easier for non-technical stakeholders to interpret.
Reference: NCARB ARE 5.0 Handbook - PjM Content Area 3: Project Work Planning


NEW QUESTION # 30
A principal architect is working with a school district on designing an 18,000-square-foot athletics training facility. During the DD phase, the principal notices that the firm's younger staff has produced equipment plans that do not coordinate with the electrical engineer's sheets.
How should the principal architect respond to the lack of coordination? Check the three that apply.

  • A. Review checklists with the staff
  • B. Conduct a desk critique
  • C. Hold a design charrette
  • D. Extend the design schedule
  • E. Schedule an immediate coordination meeting
  • F. Coordinate drawings in submittal review

Answer: A,B,E

Explanation:
These three actions represent proactive and constructive responses to coordination issues during the Design Development (DD) phase.
A). Review checklists with the staff: Using coordination checklists reinforces quality control standards and helps less-experienced staff identify typical coordination pitfalls.
D). Conduct a desk critique: This one-on-one review allows the principal to mentor younger staff, identify specific problems, and ensure corrections are made early.
E). Schedule an immediate coordination meeting: Critical to resolving discrepancies quickly with the electrical consultant and design team to realign the design set.
Incorrect options:
B). Design charrettes are typically used for creative brainstorming in schematic design, not resolving coordination issues in DD.
C). Extending the schedule is a last resort and not an efficient first step.
F). Submittal review happens during construction and is too late for addressing design-phase coordination issues.
ARE 5.0 PjM References:
NCARB ARE 5.0 Handbook - PjM: "Consultant Coordination & Document Quality Control" AHPP, 15th ed., Chapter 11: Design Phases and Staff Management Quality Management Plan strategies during DD and CD phases Let me know if you'd like follow-up questions or explanations from other divisions like CE, PPD, or PA.


NEW QUESTION # 31
What is the architect's primary responsibility when responding to a contractor's Request for Information (RFI) during construction?

  • A. Inspecting the contractor's work for quality
  • B. Revising the contract to include additional services
  • C. Providing a clear and timely clarification to avoid delays
  • D. Issuing a change order immediately

Answer: C

Explanation:
An RFI is a formal request from the contractor for clarification regarding the contract documents during construction. The architect's primary responsibility is to respond clearly and promptly to avoid project delays and confusion. The architect reviews the question, interprets the design intent, and provides necessary clarifications or directs the contractor accordingly. While an RFI can lead to change orders, issuing them is a separate process involving owner approval. The architect's role focuses on maintaining project momentum and communication flow. This aligns with the ARE 5.0 PjM emphasis on construction phase communication, contractor coordination, and proper documentation of clarifications as part of contract administration.


NEW QUESTION # 32
Construction of a gymnasium is scheduled to be complete 365 days from the date of the notice to proceed. On Friday, day 355 of the schedule, the contractor submits a punch list to the architect for substantial completion.
The architect agrees to review the punch list on-site after the weekend.
On Monday, the architect discovers that a subcontractor left open a skylight over the weekend, allowing heavy rain to fall into the courtyard area and damage the gymnasium floor. It was determined the flooring must be replaced. The lead time for new flooring is 8-10 weeks, and installation will take 14 days. The architect's agreement with the owner is contracted to end 30 days after substantial completion.
Which of the following documents must the architect prepare immediately? Check the two that apply.

  • A. A change order to purchase new flooring
  • B. A request for liquidated damages for contractor review
  • C. An invoice for additional services for owner payment
  • D. A revised schedule for owner approval
  • E. A punch list for areas not damaged for contractor approval
  • F. A notice to the contractor for withholding final payment

Answer: A,E

Explanation:
The punch list is valid only for work deemed substantially complete. Since the floor is damaged, substantial completion cannot yet be certified, but the architect can and should prepare a punch list for other non-affected areas. Meanwhile, the replacement flooring constitutes a change in scope, requiring a change order. The contractor, being responsible for the damage, will need to correct the work per the General Conditions (A201).
Incorrect choices:
A). The contractor revises the schedule, not the architect.
B). The owner assesses liquidated damages, not the architect directly.
C). No additional services have been performed yet.
E). Final payment withholding applies after project closeout, not now.
References:
AIA A201-2017 §§ 9.8-9.10
AIA B101-2017 §§ 3.6.2 & 4.2.3
NCARB ARE 5.0 Handbook - Construction Phase Services


NEW QUESTION # 33
A new restaurant design must incorporate specific light fixtures to meet the franchise requirements. The owner conveys this to the architect, who must make sure that prospective bidders do not overlook specific fixtures.
Which method should the architect use during the construction documents phase?

  • A. Issue an addenda that highlights the franchise branding requirements
  • B. Identify the fixtures in the performance specification
  • C. Note and clearly identify the specific light fixture in the drawings

Answer: C

Explanation:
The most effective way to ensure that specific fixtures are not overlooked by bidders is to clearly indicate them directly in the construction drawings. This makes the requirement highly visible and enforceable, as drawings are primary references for pricing and execution.
While specifications are important, drawings are usually the first point of reference for contractors during the bidding and construction phases.
Including the light fixture directly in the drawings removes ambiguity and reinforces the requirement.
Reference: NCARB ARE 5.0 Handbook - PjM Content Area 4: Project Quality Control Reference: AIA A201 General Conditions of the Contract for Construction


NEW QUESTION # 34
Which of the following is a primary responsibility of the architect during construction observation?

  • A. Issue building permits
  • B. Inspect the work for conformity to the contract documents
  • C. Supervise contractor's workforce
  • D. Manage contractor's payroll and payments

Answer: B

Explanation:
During construction observation, the architect inspects the work to confirm compliance with contract documents, identifies deficiencies, and documents progress. The architect does not supervise or manage contractor workforce or finances, nor issue permits. This observation helps verify quality and adherence to design intent. ARE 5.0 PjM covers the architect's limited but critical role in construction administration and quality control.


NEW QUESTION # 35
While conducting a site visit for a residential tower delivered through the design-build method, an architect observes several construction workers without hard hats and other unsafe working conditions.
How should the architect proceed?

  • A. Immediately instruct construction workers on which safety precautions need to be taken.
  • B. Request that the contractor review safety precautions that need to be taken with construction workers.
  • C. Document the unsafe working conditions and send a memo to the contractor copying the owner.
  • D. Document the unsafe working conditions and send a memo to the owner copying the contractor.

Answer: C

Explanation:
Although safety is primarily the contractor's responsibility (per AIA A201), the architect has an ethical and limited contractual obligation to report unsafe site conditions observed during site visits. The correct action is to document the issue in writing and notify the contractor, while copying the owner. Directing the contractor's crew is outside the architect's authority.
References:
AIA A201 - Article 3.3 and 4.2.2
NCARB ARE 5.0 Handbook - Site observations and safety protocols
AIA Code of Ethics - Obligation to protect public health and safety


NEW QUESTION # 36
The management of architectural projects by a project manager consists of which responsibilities? Check the four that apply.

  • A. Providing liability insurance
  • B. Producing construction documents
  • C. Planning, organizing, and staffing the project
  • D. Monitoring progress
  • E. Facilitating the work
  • F. Concluding the project

Answer: C,D,E,F

Explanation:
The project manager's role in architectural projects is centered on overseeing and guiding the project from inception through completion. The key responsibilities include:
* Planning, organizing, and staffing the project (B):The project manager is responsible for organizing the project team, assigning roles, and ensuring that the project is staffed with the appropriate personnel.
* Facilitating the work (D):This involves coordinating communication, resolving conflicts, and ensuring smooth collaboration among team members and consultants.
* Monitoring progress (E):The project manager tracks project milestones, schedules, budgets, and quality control to ensure the project stays on track.
* Concluding the project (F):This includes finalizing all project documentation, conducting closeout meetings, and ensuring all contractual obligations have been met.
Responsibilitiesnot typically partof the project manager's role:
* Producing construction documents (A):This is the responsibility of the design team (architects, drafters, and consultants), not the project manager per se.
* Providing liability insurance (C):This is an administrative or firm responsibility, not a direct function of the project manager managing the project.
References from ARE 5.0 Project Management (PjM) division:
* Roles and responsibilities of the project manager in architectural projects
* Project management principles: planning, organizing, staffing, monitoring, and closing projects
* NCARB ARE 5.0 PjM study materials discussing project manager duties and scope
* AIA contract and management guidelines emphasizing project management functions


NEW QUESTION # 37
A construction project is one week away from the date of substantial completion as defined by an AIA A201 agreement. The owner comes forward with a major change to the work. The contractor and owner disagree on how much to extend the contract time. The project needs to proceed without delay while the contractor and owner work out the difference.
Which one of the following steps should the architect take?

  • A. Issue a minor change in the work.
  • B. Issue a waiver of subrogation.
  • C. Issue a construction change directive.

Answer: C

Explanation:
When there is a disagreement over cost or time but the work must proceed, the architect can issue a Construction Change Directive (CCD). This allows the work to move forward while the owner and contractor negotiate terms. A Minor Change (B) is only for non-cost/time changes. Waiver of Subrogation (C) pertains to insurance.
CCDs are used under AIA A201 §7.3 when immediate work is needed but consensus hasn't been reached.
This is the formal process to avoid delay in project delivery.
Reference: AIA A201 §7.3 - Construction Change Directives
NCARB ARE 5.0 Handbook - PjM Content Area 5


NEW QUESTION # 38
After redesigning an existing restaurant, the architect submits the plans to the county for building permit review. During the Zoning Review, the county requests the architect submit a site plan for review and approval. After researching the county's records, the architect discovers a 40-year-old approved site plan that is stamped, "Approval is based on the site plan and usage as indicated. Any interior partitioning of the original building will be subject to review and approval by the county." How should the architect proceed?

  • A. Submit the county's historical drawing that references the approved site plan
  • B. Require the client to contract with a civil engineer to update the site plan
  • C. Hire a consultant civil engineer to develop an updated site plan

Answer: B

Explanation:
It is the architect's responsibility to inform the client that an updated site plan is required for zoning compliance. However, preparing the site plan is typically the scope of a civil engineer. Therefore, the architect should require the client to hire a civil engineer to prepare and update the site plan.
Architects are responsible for coordination but not directly preparing civil site plans unless within their licensure and scope.
This aligns with standard architectural services and professional boundaries.
Reference: AIA B101 Owner-Architect Agreement - Article 3: Scope of Architect's Basic Services NCARB ARE 5.0 Handbook - PjM Content Area 1: Resource Management


NEW QUESTION # 39
Which four factors will most affect the choice of project delivery method? Check the four that apply.

  • A. Building code
  • B. Construction cost
  • C. Project scope
  • D. Owner capabilities
  • E. Owner risk tolerance
  • F. Size of architectural firm

Answer: B,C,D,E

Explanation:
A). Project scope: Impacts complexity and integration needs.
C). Owner capabilities: Determines whether the owner can manage multiple contracts (as in DBB or CM).
E). Risk tolerance: Risk-averse owners may prefer DB or CM-at-risk with cost guarantees.
F). Construction cost: Influences whether fast-tracking or GMP methods are needed.
Incorrect:
B). The firm's size is rarely a determining factor.
D). Code compliance is required in all methods but doesn't drive delivery choice.
References:
AHPP Chapter 10 - Choosing a Delivery Method
NCARB ARE 5.0 Handbook - Delivery Method Evaluation Criteria


NEW QUESTION # 40

Design Firm ABC is awarded two projects, but they do not have enough staff to support the execution of both projects due to unexpected staffing issues. ABC is deciding if they need to hire staff from an outside firm to execute the projects.
Which one of the following sets of staff members would adequately support ABC's staffing needs?

  • A. 1 Designer, 1 Drafter
  • B. 2 Drafters
  • C. 1 Lead Architect, 1 Drafter
  • D. 2 Designers

Answer: C

Explanation:
Comprehensive Detailed Explanation:
From the schedule:
Total lead architect hours needed = 16 + 24 = 40 hrs/week
Firm ABC only has 50% of 1 Lead Architect = 20 hrs/week # Needs 20 hrs more Total drafter hours needed = 80 + 80 = 160 hrs/week Firm ABC has 3 Drafters at 100% = 3 × 40 = 120 hrs/week # Needs 40 hrs more Thus, the firm needs 1 Lead Architect (for 20 hrs) and 1 Drafter (for 40 hrs) from the augmenting firm to meet the requirement.
References:
NCARB ARE 5.0 PjM Handbook - Staffing plans and workload balancing


NEW QUESTION # 41
A project achieves refinement and coordination in which of the following phases?

  • A. Construction Documents
  • B. Schematic Design
  • C. Design Development

Answer: C

Explanation:
Design Development (DD) is the phase where schematic concepts are refined and systems are coordinated across disciplines. This includes structure, MEP, and materials. While Schematic Design focuses on high- level form and layout, and Construction Documents focus on detailed drawings/specifications, DD ensures integration and alignment before detailing.
References:
NCARB ARE 5.0 Handbook - Design phases
AIA B101 - Design Development phase scope


NEW QUESTION # 42
......

Validate your Skills with Updated Project-Management Exam Questions & Answers and Test Engine: https://www.testkingpass.com/Project-Management-testking-dumps.html

Tested & Approved Project-Management Study Materials Download: https://drive.google.com/open?id=18_KH6_aUE-bqtt2WPVLoXwkiluFA1PDh